PROJECT SUMMARY
Dynamo designed a greenfield substation and medium voltage distribution for a canola processing facility near Yorkton, SK.
PROJECT SUMMARY
SECTOR:
Chemical
CLIENT:
Yara Belle Plaine Inc.
DURATION OF PROJECT:
8 Months
PROJECT SUMMARY:
Evraz NA is a global steel and mining company and the leading producer of infrastructure steel products in North America. They are among the top 30 steel producers in the world and own and operate major assets in Russia and North America.
Dynamo was retained to reconfigure the primary and secondary cables for 85.NUT.67 distribution transformer. The top-entry configuration of the existing cabinets were severely compromised due to the corrosive environment and water entering the compartments through the cable entry point.
New stainless-steel cabinets were designed, fabricated, and installed by Dynamo. The 13.8 kV primary cables and the 5 kV secondary cables were removed and replaced with 15 kV and 5 kV single conductor 350 MCM cables.
Engineering began in early 2015 before the removal, installation, cable terminations, and commissioning were completed in the fall of 2015.
Recent Posts
Dynamo designed a greenfield substation and medium voltage distribution for a canola processing facility near Yorkton, SK.
Dynamo was retained to complete the decommissioning and disposal of one (1) 20 MVA transformer, BU-410-TX-1 and one (1) high voltage oil circuit breaker, BU-410-TX-1-OCB at the Bethune Station and one (1) 20 MVA transformer, ZP-420-TX-2 at the Loreburn Station.
Dynamo was retained to fabricate, ship, and install a 9.6 m x 4.5 m control building for the Grenfell Substation. Drawings were supplied by Dynamo based on a preliminary design provided by SaskPower.